Why 35-45 days are required for finished product production?
Often customers will ask this question. Why
does your product produce 35-45 days?
Let me tell you the production process:
Confirm Order - Sign Contract - Prepayment
Deposit - Confirmation Details (including LOGO, Packaging, Logistics) -
Production Production Requirement Form - Purchase Ordered Raw Materials
(usually a product has more than 20 types of materials, different suppliers
have different material delivery dates) - Confirmation of the proofing (7 days)
- The materials are ready for inspection AQL - Assembled - Finished product
inspection - Completed shipment - Logistics - Shipment.
In many cases, we advise customers to take
inventory, because we have 5,000 in stock for each electric pencil sharpener
and electric eraser.
It takes only 5 days to ship.
If you have other questions, you can ask me